Regulator: Medicines and Healthcare products Regulatory Agency (MHRA)
ICSR reporting timelines
Serious (post-marketing)
15 calendar days
Non-serious (post-marketing)
90 calendar days
Clinical trial
Fatal or life-threatening unexpected serious adverse reactions (SUSARs) must be reported as soon as possible, but no later than 7 calendar days after the sponsor has first knowledge of the case. A follow-up report should be submitted within an additional 8 calendar days. All other SUSARs must be reported as soon as possible, but no later than 15 calendar days
Foreign vs. domestic submission
Both domestic (UK) and foreign (non-UK) serious ICSRs must be submitted to the MHRA. Non-serious only domestic.
PBRER / PSUR / PADER requirements
Pharmaceutical companies to submit PSURs/PBRERs based on the dates set by the European Medicines Agency (EMA) and within 70 calendar days of the data lock point (day 0) for PSURs covering intervals up to 12 months (including intervals of exactly 12 months); and within 90 calendar days of the data lock point (day 0) for PSURs covering intervals in excess of 12 months; the timeline for the submission of ad hoc PSURs requested by national medicines authorities will normally be specified in the request, otherwise the ad hoc PSURs should be submitted within 90 calendar days of the data lock point.
Risk management plan (RMP)
An RMP with a focus on UK-specific risk minimisation measures is required.
Local QPPV requirements
QPPV is required. Must be a resident in UK, or EU QPPV with national contact in UK
PSMF requirements
A PSMF must be maintained for UK authorised products.