Regulator: Ministry of Public Health, National Pharmacovigilance Center (CNPV)

ICSR reporting timelines

Serious (post-marketing)

15 calendar days

Non-serious (post-marketing)

90 calendar days

Clinical trial

Fatal or Life-Threatening Unexpected Serious Adverse Reactions (SUSARs): Sponsors are expected to report these events to the Kuwaiti MOH as rapidly as possible. The standard international timeline is no later than 7 calendar days after the sponsor first becomes aware of the event. A detailed follow-up report is typically required within an additional 8 calendar days. All Other Unexpected Serious Adverse Reactions: For all other serious adverse reactions that are not fatal or life-threatening but are unexpected, the reporting timeline is no later than 15 calendar days after the sponsor's initial awareness of the case.

Foreign vs. domestic submission

Only domestic cases are required to be submitted

PBRER / PSUR / PADER requirements

Pharmaceutical companies to submit PSURs/PBRERs based on the dates set by the European Medicines Agency (EMA) and within 70 calendar days of the data lock point (day 0) for PSURs covering intervals up to 12 months (including intervals of exactly 12 months); and within 90 calendar days of the data lock point (day 0) for PSURs covering intervals in excess of 12 months; the timeline for the submission of ad hoc PSURs requested by national medicines authorities will normally be specified in the request, otherwise the ad hoc PSURs should be submitted within 90 calendar days of the data lock point.

Risk management plan (RMP)

Preparation of the risk management plan should follow the RMP template annexed in the “Arab Guidelines on Good Pharmacovigilance Practices” For all new MA applications requiring an RMP, a risk management plan describing the risk management system that the MA applicant will implement for the medicinal product concerned must be submitted. Other situations in which a RMP or an update thereof is required are: - an application involving a significant change to an existing MA (new manufacturing process for a biological drug, pediatric indication or other significant change in the indication, etc.), - at the request of the health authorities when there is a concern about a risk affecting the benefit-risk balance, - upon submission of final study results impacting the RMP, - upon submission of a PSUR for a drug when the new data in this PSUR directly affect the RMP, - at the time of renewal of an MA application, if the product has a RMP.

Local QPPV requirements

The MA Holder must have, on a permanent and continuous basis, an appropriately qualified person responsible for pharmacovigilance (QPPV) based in Tunisia. For foreign laboratories holding a marketing authorization, in addition to the QPPV appointed at headquarters, a local pharmacovigilance manager (LSR) attached to the QPPV, based in Tunisia, is required.

PSMF requirements

The file of the local pharmacovigilance system (PSSF) which describes the main elements relating to pharmacovigilance activities in Tunisia.